Decision details

WATERSIDE REGENERATION AREA - Use of Compulsory Purchase Powers - Leicester Waterside - Phase 1

Decision Maker: City Mayor (Individual Decision)

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve to declare and make a CPO to acquire any property interests and rights not already acquired, which are required for the proposed Leicester Waterside-Phase 1 Project as identified on the plan in the Appendix 1.  Although negotiations are currently underway to acquire all the required property interests and rights by agreement, approval is sought to start the compulsory purchase process to acquire the identified property and rights and run it in parallel with the current negotiations.

Decision:

1)         The City Council declare and subsequently make a Compulsory Purchase Order pursuant to Section 226 (1) (a) of the Town and Country Planning Act 1990, for the purpose of acquiring the land and rights identified in Appendix 1 of the report (the Order Lands). This is required to carry out the development, redevelopment or improvement of the land to deliver the Leicester Waterside-Phase 1 Project. 

 

The formal making of the Order will be subject to:

 

(a)       The Council ensuring that all reasonable steps have been taken to acquire the required interests in the land by agreement.

 

(b)       A resolution by Full Council to secure the necessary funding to carry out the CPO property interests and rights acquisitions and associated compensation claims and the subsequent infrastructure works.

 

(c)       The Council ensuring that satisfactory progress is achieved with a developer to undertake the scheme.

 

2.         The City Barrister & Head of Standards be authorised to advertise the making of the Order referred to above and take all relevant action thereon to promote the confirmation of the Order.

Reasons for the decision:

To declare that the Compulsory Purchase Order process will be started to acquire the identified property and rights to run in parallel with the current negotiations to acquire the land and interests by agreement.    

Alternative options:

To continue to carry on negotiations to acquire by agreement the property interests required for the scheme.

Publication date: 08/04/2016

Date of decision: 18/04/2016

Effective from: 26/04/2016

Accompanying Documents: