The Director of Finance submitted a
report to show the position of the capital programme at the end of
December 2023 (Period 9).
The Committee was recommended to consider
the overall position presented within this report and make any
observations it saw fit and note the quarterly prudential
indicators presented in Appendix F.
The Director of Finance noted
that:
-
This was the third such report for
2023/24. As per previous reports it
continued to flag pressures and slippages.
-
Members were reminded that once pressures were
reported the ratings were reset.
-
This was the first time the report had contained the
additional index on prudential indicators. The Council had approved the Treasury Strategy in
February. This appendix confirmed that
the Council had complied with the Treasury limits.
In response to comments and questions
from members, the following was stated:
-
In response to a query about progress on the
re-opening of Jewry Wall Museum, the City Mayor reported that he
had visited the site with the media to look at progress made, and
it was hoped to open early in 2025. The
listed building had been used well and was fit for
purpose. The importance of the site as
the biggest example of non-military Roman masonry in the UK was
highlighted.
-
In terms of investment in Leicester Museum and Art
Gallery (LMAG), a long period of investment had been undertaken and
galleries had been moved around, including the important collection
of Picasso exhibits. A new café
was being developed as customers at museums often expected
refreshments, the café would make the museum more fit for
purpose and accessible. It was further
added that visitors would not stay long at the museum if they could
not get refreshments. The new
café was replacing the previous one as the previous
café had been at the back of the building and there was now
a better space that it could occupy.
This was only a small part of the remodelling that continued for
many years on a regionally important gallery.
-
With regard to the paintings in the gallery, the
gallery had many important paintings that were rotated.
-
Regarding works on St George’s churchyard, the
scheme had been scaled back and trees were not the major
focus. The area was currently perceived
as safe or friendly and as such work was needed. The planning applications, which included the
plans had been submitted, and were available to view.
-
With regard to city estate shops on Thurncourt Road,
these had been looked at pre-Covid. An
adequate scheme was yet to be seen. The
shops were an important part of the area they served and could
benefit from investment. The City Mayor
would ask Ward Councillors to consider and discuss how improvements
could be approached.
-
Regarding the developments at Leicester Railway
Station, it was noted it was a complex project with many parties
involved and was dependent on the availability of contractors was
being awaited.
-
It was suggested that a site visit to LMAG and Jewry
Wall Museum be arranged for members of the Committee and also
members of the Culture and Neighbourhoods Scrutiny
Commission.
-
With regard to the Lothbury fund, an extension had
been granted for the fund to see if an acquisition could
happen. This was a 60-day process, and
an update would be available shortly.
This would be updated in the Annual Treasury Report. Treasury advice would be sought once the decision
was known.
AGREED:
1)
That the report be noted
2)
That the quarterly prudential indicators
presented in Appendix F be noted.
3)
That a site visit to LMAG and Jewry Wall
Museum be arranged for members of the Committee and also members of
the Culture and Neighbourhoods Scrutiny Commission.
4)
That the City Mayor make contact with the
Thurncourt Ward Councillors in respect of possible improvements to
the Thurncourt Road shops; and
5)
That an update on the Lothbury Fund be
provided in the Annual Treasury Report.