Issue - decisions

LEISURE CENTRE CAPITAL PROGRAMME PHASE 2

19/10/2021 - LEISURE CENTRE CAPITAL PROGRAMME PHASE 2

1.    To approve phase 2 of the Leisure Improvement Programme at Spence Street, Braunstone and Aylestone leisure centres with an estimated cost of £1.94m.

 

2.    To note, in addition, the recent government Salix grant approval (£213,676), for energy efficiency measures at Spence Street gym which will be co-ordinated as part of this scheme. Subject to completing the Salix work by March 2022.

 

3.    To approve the release of £1m of policy provision for sports expansion in the current capital programme to progress the Spence Street scheme.

 

4.    To approve an addition to the capital programme of £0.94m from corporate resources to fully fund the Phase 2 schemes.

 

5.    To note utilising the National Leisure Framework to develop the Phase 2 schemes.