Decision details

CAPITAL BUDGET MONITORING APRIL - MARCH 2023/24

Decision Maker: City Mayor (Individual Decision)

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Decisions consequential to the monitoring of expenditure in 2023/24 (if any).

Decision:

To:

 

Approve the carry forwards of resources for work programmes and provisions as detailed in the report to 2024/25.

 

Approve the following additions:

 

o          £4,150k for Replacement Cladding Phoenix Square, funded by an additional government grant

 

o          £1,014k for Highways Maintenance, funded by additional government grants

 

o          £558k for Early Years – Two Year Olds, funded by a government grant

 

Approve the following transfer:

 

o          £726k from HRA revenue underspends for kitchens and bathrooms, boiler replacements, rewiring, disabled adaptations, and insulation works

 

o          £289k of corporate resources from Onsite Construction Skills Hub to revenue reserves

           

Approve the following policy provision release:

 

o          Release £380k from the Strategic Acquisitions Policy Provision for the release of a leasehold on Southampton Street to continue land assembly in the cultural quarter

 

Approve the following reductions to the 2024/25 Capital Programme

 

o          £1,000k reduction in the budget for operational property maintenance

Reasons for the decision:

The Executive and Overview Select Committee receive a report on the forecast capital budget position regularly throughout the year (as well as an outturn report at the end of the year).  Recommendations arising from this are often included within the report.

Alternative options:

Not applicable

Publication date: 07/08/2024

Date of decision: 15/08/2024

Effective from: 23/08/2024