Decision details

MUGA/ PlayZone Programme

Decision Maker: City Mayor (Individual Decision)

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To seek approval for amendments to the Multi-Use Games Area (MUGA) budget within the General Fund Capital Programme.

Decision:

To consider proposals to approve:

 

1.         The addition of £1,858k to the existing MUGA budget within the General Fund Capital Programme, financed from the Football Foundation grant funding.

 

2.         The use of £705k of existing MUGA budget as match-funding, to enable acceptance of the Football Foundation grant.

 

3.         The addition of £443k to the existing MUGA budget within the General Fund Capital Programme, financed from S106 contributions.

 

4.         The addition of £28k to the existing MUGA budget within the General Fund Capital Programme, financed from OPCC grant funding.

 

Alternative options:

           To not proceed with the additional funding and retain the original budget allocation, thereby reducing the number of ball courts being built or refurbished.

 

           To only partially proceed with the additional funding such as S106 funding and/or the OPCC funding, thereby not proceeding with the Football Foundation funded projects.

 

To only partially proceed with the additional funding such as the Football Foundation funded projects, thereby not proceeding with the S106 funded projects

Publication date: 04/07/2025

Date of decision: 14/07/2025

Effective from: 22/07/2025

Accompanying Documents: