St Martin's Link

Decision Maker: City Mayor (Individual Decision)

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: Yes

Decision:

To:

 

a.         approve the St Martin’s link scheme, with a total scheme cost of £3.5m;

 

b.         note the £2.42m already approved within the capital programme for 1

2-20 Cank Street Link (a previous version of this scheme);

 

c.         approve the transfer of £1.08m budget from the Transport Improvement Works programme earmarked for transport schemes such as this.

Reasons for the decision:

Development of a connecting walkway link between St Martin’s and Green Dragon Square

Alternative options:

Options considered and superseded including scheme to partially retain buildings and create a narrower walkway.

Publication date: 30/09/2026

Date of decision: 30/09/2026

Effective from: 08/10/2026

This decision has been called in by: