113 TRANSFORMING THE LEARNING ENVIRONMENT (TLE) PROGRAMME STRUCTURE AND BUDGET PDF 117 KB
Councillor Dempster submits a report that proposes changes to the existing Children and Young People’s Services (CYPS) Property Services Team and Building Schools for the Future (BSF) Team to deliver the Council’s capital programme for children and young people. Cabinet is asked to approve the recommendations set out in Paragraph 3 of the Report.
A minute extract from the meeting of the Children and Young People’s Scrutiny Committee held on 26 November 2009 will be circulated as soon as it is available.
Additional documents:
Minutes:
Councillor Dempster submitted a report that proposed changes to the existing Children and Young People’s Services (CYPS) Property Services Team and Building Schools for the Future (BSF) team to deliver the Council’s capital programme for children and young people. Councillor Dempster explained that it was intended to put together one team to deal with capital projects to ensure an integrated strategy to obtain best value. It was noted that at one time the use of consultants had been necessary, but such work was now able to be carried out by Officers.
It was noted that the Children and Young People Scrutiny Committee had considered the report at its meeting on 26 November 2009 and had noted the report and endorsed the recommendations for Cabinet.
RESOLVED:
that Cabinet:
1. Approves the proposed Transforming the Learning Environment (TLE) Division structure as set out at Appendix A of the report.
2. Approves the TLE Programme budgeted expenditure for 2009/10 and 2010/11 as set out at Appendix B of the report.
3. Approves in principle the TLE Programme budgeted expenditure for 2011/12 to 2013/14 which will be subject to further Cabinet approval nearer the time (Appendix B).
4. Approves the application of the funding identified at Appendix B, subject to a review and further approval for 2011/12 onwards nearer the time.
5. Supports the creation of a TLE earmarked reserve, to which the one-off funding would be credited and on which interest would be paid annually; and
6. Approves the capitalisation and addition of £1,169,000 of BSF development costs to the 2009/10 capital programmes, funded by Dedicated Schools Grant.