The Director
of Neighbourhood and Environmental Services submitted a
presentation about the Selective Licensing Scheme and provided an
update on the data recorded up to 31 December 2022.
The Deputy City Mayor for Culture, Leisure, Sport
and Regulatory Services introduced the presentation, noting that
the aim of the scheme was to improve the standard of housing in the
private sector.
The Head of Regulatory, Neighbourhood and
Environmental Services presented information about the Selective
Licensing Scheme which included a summary of the scheme headlines;
application and inspection processes; hazards and images of hazards
identified; and plans around future
communications.
It was noted that:
- The scheme went live
on the 10th October 2022.
- A team had been
recruited to resource the scheme, which consisted of a Team
Manager, an Admin Manager, two Senior Regulatory officers, 17
Housing Inspectors and three Admin Support Officers.
- There were three
cluster areas in the scheme, Fosse, Stoneygate and Westcotes Wards,
and across the area there were around 8500 properties that fall
into the private rent sector.
- In terms of data, at
this point 413 applications had been received; 213 inspections had
been carried out. 35 draft licenses and 42 full licenses had been
issued.
- A new computer system
had been introduced, which helped to streamline the process and
capture more data, this enabled the team to action applications in
a more efficient way.
- The Selective
Licensing Team were currently working to develop a digital
inspection process, that would enable officers to complete
inspections digitally using tablets, and to upload the data when
they returned to the office.
- The Scheme was within
budget, with the original aim of the scheme, to self-fund the
department using resources generated from the scheme, successfully
being adhered to and avoiding the possibility of the scheme being
operated at a loss.
- All information
regarding the scheme was available on the Councils website. A post
code checker was available for landlords to check if their property was included in the scheme area
before making an application. There was also a telephone line for
support.
- Once
an inspection had been carried out, if only minor issues were found
a draft license could be issued until the works were carried out.
Major issues would need to be resolved before a draft license could
be issued.
- The
current turn around for applications was 7 weeks, with an average
of 32 days to issue a license. Which was within
target.
- The
scheme was due to run for 5 years.
- The
aim was to undertake 3 inspections of a property over the 5 years
of the scheme.
- The
scheme was being operated alongside the Housing, Health and Safety
Rating System, which was a national scheme and provided consistency
across all Local Authorities for assessing hazards within private
rented properties. It covered 29 hazards in total which were
split
across two categories. Category 1 – Serious
and immediate risk. Category 2 – Less serious
hazards.
- Hazards were found in 46% of inspections, split approximately as
40% in Category 1 and 60% in Category 2.
- Work
was in progress in conjunction with City Wardens to identify
properties of concern and refer those to the
scheme.
- A
quarterly newsletter would be sent to landlords from January
2023.
- An
early bird discount was currently available to landlords until
April 2023, which would reduce the fee from £1090 to
£750. Additional press releases were due to be advertised to
encourage landlords to come forward.
- Support sessions for landlords were being planned in libraries
across the district.
In response to Members’ questions, it was
noted that:
- The
scheme costs had been based on how many applications were expected
to be received and the number of private rented accommodations in
the area. This was compared against the resources needed to inspect
that property over the 5-year period, plus any follow up
work.
- The
overall cost of the scheme for 5 years was £8.65M, with
£5.9M being staffing costs. The remaining balance were
overheads plus the cost of the discounted fees.
- The
expected number of applications was 7,900, which worked out at an
average cost per license of £1090.
- Once a
property had been inspected, they would receive a full license if
no action was required. If actions was required, a draft license
would be drawn up, in which the landlord would have 14 days to
appeal or challenge the decision. After 14 days, if nothing were to
be raised, a full license would be issued.
- If the
actions requested were not completed, the Council would have the
right to rescind the license. If the issues were minor, existing
housing enforcement powers could be used to issue an improvement
notice.
RECOMMENDED:
That the Commission receive a report providing an
overview of the Selective Licensing team’s work in six
months’ time