Cllr Dawood arrived at the beginning of this
item.
The Director for Estates and Building Services
submitted a report on Energy efficiency schemes in private sector
housing in the city.
The Service Manager for Sustainability attended the
meeting to make the presentation and assist with discussion and the
Team Leader for Energy Projects attended the meeting remotely to
assist with discussion.
Slides were presented as attached in the agenda
pack.
Key points included:
- A
large percentage of housing within the city was terraced or
semi-detached and 36%was built before 1929. This meant that many of these had solid walls and
as such were energy inefficient and needed work to bring up to
standard, such as by applying external wall insulation with
finishes that retained the character of the building.
- Co-benefits included:
- Reducing fuel poverty and addressing the cost-of-living crisis
– Vulnerable people in the UK spent a higher percentage of
their income on energy than those in Europe.
- Reducing damp and mould and improving internal air quality
– Recent events as reported in the media had led to a big
push on the issue.
- Health
benefits to residents – both physical and mental.
- Climate justice – supporting vulnerable groups as climate
change mitigation moved forward – lower carbon heating could
mean higher costs, so there was a need to support the most
vulnerable.
- Creating local jobs in retrofit installation.
- Improving the local economic buying power of residents –
if residents had more disposable income as a
result of lower energy bills, they could spend more in the
local economy.
- There
had not yet been much research into the impact on homes as the
climate warmed, but a watching brief was being kept on research as
it came in to ensure that retrofitting was appropriate.
- In a
good retrofit, an assessment was undertaken both in needs of the
physical aspects of the property and how the owners of the property
were using that property. Following
this a whole-house plan was prepared.
Once that plan was complete, options were considered such as
upgrading the fabric of the building, looking at heating options
and looking at renewable technologies.
- Barriers to retrofit included:
- Solid
wall properties – these required internal or external
insulation.
- Inaccessible lofts.
- Disrepair – such as loose gutters and pipes that would
need to be fixed prior to external insulation being
installed.
- Homes
in conservation areas – in these cases it was necessary to
ensure that actions fitted the planning requirements.
- The
cost of redecoration following works.
- Compliance with the requests of the occupant – some
occupants may pay more for a brick-strip effect.
- Overall costs – these had increased since the Covid-19
pandemic and the cost-of-living crisis.
- Ensuring the availability of properly trained staff.
- If all
retrofitting was completed as desired in the city, 86% of city
properties
could be brought up to Energy Performance Certificate (EPC)
level C or above, however, the cost of this would be
prohibitive.
- In
terms of grant schemes since October 2020 – Schemes had been
difficult to administer and run and had taken time to get
going. Figures were relatively low for
Phase 1. Whist lots had been achieved
in phase 2, this also covered social housing which was easier to
achieve. The Local Authority Delivery
(LAD) 3 had been the most successful scheme in both Leicester and
nationally. This had been delivered
well in the private sector. The Home
Upgrade Grant (HUG) scheme was only available for off-gas
properties, and there was no national scheme from the government
for vulnerable houses on gas.
- ECO
was a government efficiency scheme funded through energy company
obligation. This was money from energy
suppliers that installers could apply for and was not run by Local
Authorities.
- In
terms of achievements through the Green Homes Grant (GHG) and LAD
schemes, LAD 3 had been the most successful. All of the money given
to them had been spent and a further £1.3m had been bid for
at a later stage and then used. Since
it had been difficult to identify off-gas homes for the HUG scheme,
the surplus money had been spent in LAD 3.
- Residents in New Parks who had benefitted from the schemes were
happy, but it was recognised that there was more to do in terms of
what was needed.
- The
HUG 2 scheme was coming up, however, there were not many off-gas
homes in the city.
- Schemes were promoted to landlords through libraries and
neighbourhood centres. Stalls had been run in various locations and
an email had been sent out showing the schemes available for
Leicester residents.
- Warm
Home Surveys would let householders know what needed to be done and
would refer people to grant schemes.
This was being promoted through multiple channels including local
radio.
- The
Council were working with EON on retrofit schemes. In addition,
currently creating a scheme with EON using ECO funding on
particular streets. This will reduce
number of rogue installers as LCC is confident that EON installers
will work to PAS2035 standard. and in line with Planning
policies. Data would be obtained on
what was being completed.
- Information on projects in progress, links and joined-up working, and how far was still
needed to go, was presented in the slides as attached to the agenda
pack.
- It was
clarified that the figures had been updated since the slides had
been produced. There were now 59 homes
that had applied for the HUG 2 grant and 38 homes that have applied
for the Warm Homes Survey. 647 Homes
had now registered under ECO 4.
The Committee were invited to ask questions and make
comments. Key points included:
- The
take-up of grants from landlords had not been high, and of those
that had enquired many had not followed through when they were
informed that they would need to contribute a third of the
costs. Despite this, the Council were
still trying to promote the scheme.
- External wall insulation had proven difficult to deliver within
costs, and many had not been in favour of internal wall insulation
when external wall insulation had not been possible. It was not thought that there would be much
success in delivering internal wall insulation as it required lots
of work with windowsills, shelves and
sockets, which could be obstructions.
The Planning team had tried to be flexible where possible and were
trying to come up with as many compromises as possible to have
external insulation.
- Many
buildings had detail on their facades and contractors were being
engaged to influence activity prior to planning
applications. The Council led by
example by demonstrating through council properties what could be
achieved.
- A
trial was being carried out by the Housing department retrofitting
on a terraced house in a way that retained detail but also complied
with the standard for retrofitting.
Since all retrofits needed to meet the standard, this was important
to address. Poor practice in other
authorities had shown potential issues, such as water getting
behind insulation that caused severe problems, therefore it was
important to fully think retrofits through.
- In
terms of property licensing, there was a condition for properties
to be EPC level 3 or above to obtain a licence.
- Regarding concerns that landlords may have over losing more
money than they got back, it was clarified that landlords only had
to pay £3k before they could apply for an
exemption.
- The
slides laid out what would be achieved if all energy efficiency
measures could be completed. However,
it was reiterated that the cost was prohibitive. The exact figures would be obtained.
- In
terms of barriers to retrofitting.
Funding was an issue, however, there were other barriers such as
disruption to tenants. However, as
energy costs increased, people would not want to spend so much of
their income on staying warm, therefore it was thought that
retrofitting would rise up
people’s agendas. Even if all the
desired funding was available, there would still be barriers,
however there were ways of working with tenants to overcome
them.
- The
current level of EPC level C homes was 36% and the potential was
86% if all stock was retrofitted. This
was an aspiration rather than a target and it showed the nature of
the challenge.
- Some
homes that had been upgraded early had been disqualified from
future schemes.
- The
figures were from the national data set and were not broken down by
city. The most relevant data therefore
was the data for the East Midlands.
- It was
suggested that it might be useful for officers to come to Ward
Community Meetings to disseminate information to tenants and
residents, perhaps with a brief presentation on what could be
offered and what could be offered to that Ward in
particular.
- Hydrogen-powered heating was not yet being considered as the
technology was still in development, however the research was being
followed closely. Many people had not
wanted to take part in trials due to safety concerns. It was thought that the technology would not be
available for a long time and as such heat pumps were unlikely to
become obsolete in the near
future. At this time there were
not many other options than heat pumps.
- The
team were not involved in delivering district heating but would
endeavour to find out whether metering would be a big burden on
tenant’s budgets.
- Currently there were no schemes aimed at middle-income
households. However, National Energy
Action had held a conference and there were loan schemes available
whereby loan companies offered low-interest loans to private
householders to take measures and make repayments. There were currently no schemes from central
government, however, it was thought that the Department of Energy
were putting work into Green Finance and ‘green
mortgages’ were offered by some banks. Additionally, energy advice could help to save
money on intervention.
- Staff
(including front-line staff) across the Council were working to
keep the community informed. Part of
the reason for the Warm Home Survey was to ensure that retrofits
were done correctly, and advice could be given.
- Regarding issues with contractors conducting work before
planning permission was granted, the Council were working closely
with EON regarding where grants went and ensuring people had
correct advice. The Council tried to be
as involved as possible so as to
mitigate issues. Installers were
registered by the Council, but it appeared as though some had done
work without informing tenants that planning permission was
required. Both the Council and EON were
working to ensure that tenants were informed correctly. If it became apparent that contractors were
informing tenants incorrectly and including the Council logo on
their leaflets, Trading Standards would be informed.
- The
timeframe was to reach net zero by 2030, however, it was noted that
the costs involved in reaching this would be high.
- It was
not thought that all homes would be retrofitted by 2030, however,
there was no alternative way of doing it as homes needed to be
retrofitted. It was important that the
Council did all it could before 2030.
- The
idea of heating a person rather than a house (i.e. with electric blankets etc.) had been discussed
with energy firms and the national grid. However, it was noted that to do so would risk
damp, mouldy houses and the associated health risks. All options were considered to address the heating
issue. It was requested that
alternative options be laid out in future reports.
- It was
difficult to obtain data on individual energy bills to assess the
benefits of retrofitting and the relative benefits of different
forms of retrofitting, however, modelling software appeared to
favour external insulation over internal due to thermal mass
(bricks retaining heat after heating had been switched
off). It was suggested that an attempt
to gather such data could be made in relation to the works in New
Parks.
AGREED:
1)
That the report be noted.
2)
That the comments of the Commission be
noted.