The Assistant City Mayor for Adult Social Care introduced
the item, noting that this was a ten-year plan, setting out requirements for
those with social care needs.
The Director for Adult Social Care and Commissioning
provided an overview of the report. Key points to note were:
- The accommodation plan was
set out across a ten-year period.
- The strategy target was to
provide 551 units of accommodation over 3 phases of delivery.
- Phase 1 had a predicted
delivery of 155 units. This target had not been met, largely due to lack
of progress with the Tiling and Hamelin Road sites.
- Phase 2 would provide 66
units.
- Phase 3 was expected to
provide 289 units.
- 56 units of accommodation
had been successfully delivered over 11 sites.
- There was a key focus on
bespoke provision.
- An excellent portfolio of
support already existed within the city.
- There was a comprehensive
range of accommodation with different models of support. Some having
communal hubs and others having floating support.
- Schemes were designed to
meet different needs, such as mental health, learning ability and physical
issues.
- There were 698 units with
supported living accommodation. This was spread over 112 schemes.
- A similar methodology to
the one underpinning the 2021 strategy was in place and would remain until
2027.
- The successful work of the
Operational Placement Team was noted, with positive outcomes in securing
the best accommodation for people needs and requirements.
- The total number of
supported people across the city currently came to 550.
- 150 older people were
living in extra care schemes.
- There was a variety of
support schemes, with commission providers and a range of people in
receipt of Direct Payments.
- Collaborative work was
taking place with colleagues in Neighbourhoods Services and with
developers.
- The Shared Lives service
had traditionally been seen as a support for those with learning
difficulties, but a more expanded offer was to come.
- There was a range of
ongoing plans with new developments expected and a continued focus on
delivery approach.
- 22 accommodation units had
been brought forward by developers, having a confirmed delivery dates across 2025/26.
- Moving forwards, there
would be a focus on working collaboratively with Neighbourhoods and City
Development on 4 interlinked workstreams. Stage 1 of which had already
been completed.
- Other opportunities
included the asset pipeline with a view to how this could be built upon.
- There was a good prospect
to work holistically and strategically.
- Regarding procurement,
detailed conversations were required with developers and providers with an
emphasis on teamwork.
- It was acknowledged that Leicester
tended to be short on opportunity to develop land. Future talks would be
necessary with the market to consider possibilities.
- There could be
opportunities with local partners, such as Leicestershire County Council
and other schemes bordering the city.
In response to questions from the committee, it was noted
that:
- The Tiling and Hamelin
Road procurement was unsuccessful due to a number of
reasons including providers uncertainty over the mixed model. On returning
to market, there appeared to be interest but this
was not substantiated at procurement.
- There was a £5.9m in
budget in Policy Provision for extra care. Models may need to be revised
in line with change.
- Positive associations with
developers included Right To Buy and Homes
England funding. Schemes tended to come with funding and might be investor
lead. Mixed financial models were welcomed.
- The commission queried
risks on working with multiple developers, Officers highlighted benefits
of having a wider pool. Checks and balances were in place. Tenants could
choose a different provider if they so wished, without risk to tenancy.
Agreed:
- That the report be noted.
- For scrutiny to follow
matters of budget and any inconsistencies arising.
- Concerns were noted on
slippage.
- Numbers of providers to be
monitored.
- Progress would be followed
with a planned return to scrutiny.