The Head of Service presented a report on the condition and
management of the Council’s housing stock. It was noted that:
- All homes
were visited on a regular basis and the stock was currently 99.5%
compliant with the Decent Homes Standard.
- A
rolling 5-year Home Health Safety Rating System (HHSRS) inspection plan
had commenced and all homes had been visited in
the previous 5 years by an officer who was able to identify any risks and
arrange for them to be remedied.
- 2
separate IT systems had been simultaneously managed to keep track of the
stock condition.
- The
new Assets module was key to demonstrating strong compliance, along with
the resources required by technical services that managed this.
- The
report highlighted the key spending areas that were over £40 million, all
of which were agreed as part of the HRA budget. There were other
smaller-scale items at a property level, and information was held on
elements such as expected replacement timeframes.
- When
elements were due for replacement, an inspection took place to ensure work
was prioritised appropriately. The largest area for refurbishments was the
kitchen and bathrooms. The intention had been to replace all kitchen and
bathrooms but due to increasing costs and budget pressures, this was
reconsidered to ensure that all kitchens and bathrooms met the decent
homes criteria and were replaced as soon as possible.
- The
elements that were changed on a periodic basis were listed in the
report.
- Stock
condition was assessed in many ways, including:
o
When properties were void, their condition was
assessed to ensure they met the decent homes standard and disruptive works were
checked and carried out.
o
Safety inspections such as gas safety
inspections were carried out annually. The gas engineer also reported any other
areas of concern after visiting the property.
o
Tenants were able to contact the service if they
wished to make alterations or improvements in a property and as part of this,
an inspection occurred
o
Inspections occurred during mutual exchanges.
The exchange could not occur unless both properties met the decent homes
standard.
o
An established process was in place for damp and
mould complaints which allowed a 4-week turnaround period for inspections.
Priority repairs were required to be inspected and completed within 4
weeks.
o
Responsive repairs were ongoing with around
80,000 occurring annually.
o
There were 30 Neighbourhood Housing Officers who
responded to tenancy management enquiries and were also able to refer any
repairs through to Technical Services.
o
The team worked closely with other services such
as occupational health, environmental health and social workers so any concerns
could be investigated.
o
Referrals were received through customer
service.
o
Regular risk assessments were carried out of
communal spaces containing asbestos.
o
Periodic Fire Risk Assessments (FRA) were
carried out.
- The
Compliance Team was now in place, and it was intended that low-risk blocks
could now be checked as well as high-risk ones.
- IT
systems confirmed that all houses had been visited at least once in the
last 5 years.
- A
new NEC module was being implemented, which would allow the council to
interrogate the information on the housing stock better. This system would
allow asset management and Health and Safety surveys to be conducted in
real time using handheld devices, with data automatically updated in the
IT system. The module was expected to be operational by September 2025,
with some recruitment needed to support the new model.
In response to comments from Members, it was noted
that:
- Gas
safety checks were carried out by staff while EICR was carried out by
contractors and in-house staff.
- Fire
Risk Assessments (FRA) but they were completed in line with the identified
risk frequency for that block, every 12 months in high-risk blocks and
sheltered accommodation. In purpose-built accommodation, they were carried
out every 5 years. A Fire Risk Assessor was directly employed in the
division, but the vast majority of FRA were completed by
contractors.
- Many
priority works were completed within the 10-day target. However, work
occurred outside of this timescale if it was inconvenient or disruptive
for the tenant. The difficulty of access to the property was an issue in
causing backlogs.
- A
report was scheduled on Repairs and Maintenance for the next Housing
scrutiny meeting. This was intended to include damp and mould updates,
which were on a significant downward trajectory.
- Concerns
were raised that the capital work programme was based on a 16-year-old
survey. Members were reassured that before any capital work to properties
is implemented, the Housing team would re-inspect and update the available
information. £170 million had been spent on housing improvements in the
last 10 years.
- While
the Health and Safety regulations required more frequent inspections
moving forward, so far, no category 1 hazards had been identified as part
of the initial HHSRS inspection completed. The ongoing stock check had
ensured that the stock was in a good, compliant standard in line with
officers understanding. However, the process adopted was being moved to a
more regulated method.
- The
division was confident that the capital programme would be effectively
delivered, particularly given the introduction of the new IT system. A
5-year investment strategy would also be developed using the intelligence
from the HHSRS inspection to focus where investment capital was
spent.
- Members
commented that increasing the number of property MOT’s
was an investment that could save money in the long term. However,
concerns were raised around the resources required to ensure that the
inspections were carried out. In response, it was noted there was to be a
new team manager, with 6 surveyors directly employed, this woul be reviewed on an ongoing basis. Colleagues in
the private sector were going to support them with their training.
Opportunities were intended to be offered for technical staff to develop,
and the apprenticeship offer was still very strong across the trades and
craft staff. This was to support the existing apprentice
programme.
- EPC’s lasted for 10 years, but there was no current
requirement for them to be provided if it had lapsed. They were only
provided in the event of a new letting / tenant.
- The
Local Authority had been fortunate in its stock; there were lots of
traditional builds, and there were no remediation works because of
building safety. Robust decisions had been made in terms of sustainable
investments, and the division had been invested in the people and the
stock. The management of the stock had put the team in a position to
proactively identify potential issues that could be revealed by the
surveys.
- Communications
were issued prior to an appointment, as well as there being an Access
Policy so that tenants understood the purpose of the visit.
- New
recruits were to be resourced from the Revenue Budget.
- Where
there was similar house types with the same issues identified, it was
logged on the dashboard so that trends were identified, and remedial works
could be carried out.
- A
key cause of damp had been identified as ventilation, so this required
communication with tenants.
AGREED:
The commission noted the report.