The Head of Service presented a report on the
condition and management of the Council’s housing stock. It
was noted that:
- All homes were visited on a regular
basis and the stock was currently 99.5% compliant with the Decent
Homes Standard.
- A rolling 5-year Home Health Safety
Rating System (HHSRS) inspection plan had commenced and all homes had been visited in the
previous 5 years by an officer who was able to identify any risks
and arrange for them to be remedied.
- 2 separate IT systems had been
simultaneously managed to keep track of the stock
condition.
- The new Assets module was key to
demonstrating strong compliance, along with the resources required
by technical services that managed this.
- The report highlighted the key
spending areas that were over £40 million, all of which were
agreed as part of the HRA budget. There were other smaller-scale
items at a property level, and information was held on elements
such as expected replacement timeframes.
- When elements were due for
replacement, an inspection took place to ensure work was
prioritised appropriately. The largest area for refurbishments was
the kitchen and bathrooms. The intention had been to replace all
kitchen and bathrooms but due to increasing costs and budget
pressures, this was reconsidered to ensure that all kitchens and
bathrooms met the decent homes criteria and were replaced as soon
as possible.
- The elements that were changed on a
periodic basis were listed in the report.
- Stock condition was assessed in many
ways, including:
o
When properties were void, their condition was assessed to ensure
they met the decent homes standard and disruptive works were
checked and carried out.
o
Safety inspections such as gas safety inspections were carried out
annually. The gas engineer also reported any other areas of concern
after visiting the property.
o
Tenants were able to contact the service if they wished to make
alterations or improvements in a property and as part of this, an
inspection occurred
o
Inspections occurred during mutual exchanges. The exchange could
not occur unless both properties met the decent homes
standard.
o
An established process was in place for damp and mould complaints
which allowed a 4-week turnaround period for inspections. Priority
repairs were required to be inspected and completed within 4
weeks.
o
Responsive repairs were ongoing with around 80,000 occurring
annually.
o
There were 30 Neighbourhood Housing Officers who responded to
tenancy management enquiries and were also able to refer any
repairs through to Technical Services.
o
The team worked closely with other services such as occupational
health, environmental health and social workers so any concerns
could be investigated.
o
Referrals were received through customer service.
o
Regular risk assessments were carried out of communal spaces
containing asbestos.
o
Periodic Fire Risk Assessments (FRA) were carried
out.
- The Compliance Team was now in
place, and it was intended that low-risk blocks could now be
checked as well as high-risk ones.
- IT systems confirmed that all houses
had been visited at least once in the last 5
years.
- A new NEC module was being
implemented, which would allow the council to interrogate the
information on the housing stock better. This system would allow
asset management and Health and Safety surveys to be conducted in
real time using handheld devices, with data automatically updated
in the IT system. The module was expected to be operational by
September 2025, with some recruitment needed to support the new
model.
In response to comments from Members, it was
noted that:
- Gas safety checks were carried out
by staff while EICR was carried out by contractors and in-house
staff.
- Fire Risk Assessments (FRA) but they
were completed in line with the identified risk frequency for that
block, every 12 months in high-risk blocks and sheltered
accommodation. In purpose-built accommodation, they were carried
out every 5 years. A Fire Risk Assessor was directly employed in
the division, but the vast majority of FRA were completed by
contractors.
- Many priority works were completed
within the 10-day target. However, work occurred outside of this
timescale if it was inconvenient or disruptive for the tenant. The
difficulty of access to the property was an issue in causing
backlogs.
- A report was scheduled on Repairs
and Maintenance for the next Housing scrutiny meeting. This was
intended to include damp and mould updates, which were on a
significant downward trajectory.
- Concerns were raised that the
capital work programme was based on a 16-year-old survey. Members
were reassured that before any capital work to properties is
implemented, the Housing team would re-inspect and update the
available information. £170 million had been spent on housing
improvements in the last 10 years.
- While the Health and Safety
regulations required more frequent inspections moving forward, so
far, no category 1 hazards had been identified as part of the
initial HHSRS inspection completed. The ongoing stock check had
ensured that the stock was in a good, compliant standard in line
with officers understanding. However, the process adopted was being
moved to a more regulated method.
- The division was confident that the
capital programme would be effectively delivered, particularly
given the introduction of the new IT system. A 5-year investment
strategy would also be developed using the intelligence from the
HHSRS inspection to focus where investment capital was
spent.
- Members commented that increasing
the number of property MOT’s was
an investment that could save money in the long term. However,
concerns were raised around the resources required to ensure that
the inspections were carried out. In response, it was noted there
was to be a new team manager, with 6 surveyors directly employed,
this woul be reviewed on an ongoing
basis. Colleagues in the private sector were going to support them
with their training. Opportunities were intended to be offered for
technical staff to develop, and the apprenticeship offer was still
very strong across the trades and craft staff. This was to support
the existing apprentice programme.
- EPC’s lasted for 10 years, but there was no
current requirement for them to be provided if it had lapsed. They
were only provided in the event of a new letting /
tenant.
- The Local Authority had been
fortunate in its stock; there were lots of traditional builds, and
there were no remediation works because of building safety. Robust
decisions had been made in terms of sustainable investments, and
the division had been invested in the people and the stock. The
management of the stock had put the team in a position to
proactively identify potential issues that could be revealed by the
surveys.
- Communications were issued prior to
an appointment, as well as there being an Access Policy so that
tenants understood the purpose of the visit.
- New recruits were to be resourced
from the Revenue Budget.
- Where there was similar house types
with the same issues identified, it was logged on the dashboard so
that trends were identified, and remedial works could be carried
out.
- A key cause of damp had been
identified as ventilation, so this required communication with
tenants.
AGREED:
The commission noted the report.