The Director of Housing submitted a report providing an update on the
progress made on the housing division’s Housing Regulator Provider Improvement
Plan (PiP). Key points included:
- This was the first progress report since the regulator inspection
in July 2025. Since then, the
service was now in the provider improvement phase, and meeting with the
Regulator of Social Housing Team on a monthly basis, giving updates on
areas identified in the inspection.
This mainly included elements in the Safety and Quality standard
and the Tenant Engagement Standard.
- The PiP included 26 specific actions as detailed in the report.
- There is an internal Board chaired by the Strategic Director of
CDN, the Director of Housing and all Heads of Service whom meet monthly in
advance of meeting with the regulator.
- Since the PiP had been generated, five of the 26 actions had been
completed. These related to
asbestos, water safety, mutual exchanges, the Tenant Scrutiny Panel and
complaints.
- The areas were RAG rated (Red, Amber, Green). There are thirteen rated green and eight
amber on the report, but since the report was published, this had changed
to sixteen green and five amber.
- Actions had been impacted by unavoidable events, such as the winter
and the implementation of legislation such as Awaab’s Law.
- There are now 2600 out-of-category repairs, down from 6,250 in
January 2025
- There are now 315 damp and mould cases, down from 539. We are on
track to clear these down during 2026
- There had been a number of IT challenges which had caused some of
the amber ratings, such as the roll out of new complaints IT system,
health and safety and fire safety IT systems. Effective systems were already in place
for these, but the new systems would help the service to enhance reporting
and pull all information in to one location.
- 3,347 Housing Health and Safety rating inspections (HHSRS) have
been completed, up from the 2,800 noted in the report.
- The service was on track to complete the target of 60% of
Electrical Safety inspections (EICRs) by the end of 2026 and to complete
the full cycle by 2028.
In response to member questions and discussion, the following was noted:
- The report related to Council stock. With regard to registered providers,
they were subject to the same regulations and inspection regime as the
Council. Historically, there had
been a degree of governance and financial oversight of registered
providers in advance of the new Regulator.
However, they now needed to comply to consumer standards. This was not necessarily the case of
private providers, however, there were changes to renters’ rights that
would bring in new requirements for providers, and they would have to go
on a national PRS Housing register.
They would also now have to meet the Decent Homes Standard and
would need to meet Awaab’s law when they are introduced or PRS. This would bring private providers more
into line with Local Authorities and registered providers.
- A private rented sector team could inspect properties for Hazards
if reports of poor condition property is received.
- The Renters’ Reform Act would give the Council more rights to
intervene in the private rented sector.
Currently a mismatch of different licensing schemes existed,
including House of Multiple Occupation (HMO) licensing, selective
licensing and additional licensing.
If these were in place then there were more rights to go into
properties and inspect standards.
It will be the duty of the Council to uphold increased standards in
the Renters’ Reform Act
- Residents could call the Private Sector Housing team and also
report online. The team could do a
Health and Safety rating and inspection and if a Category 1 hazard was
identified then the team would negotiate and deal with the landlord. Civil penalties could be imposed.
- In terms of resources for new responsibilities under the Renters’
Reform Act, the Government provided a degree of funding. Much of this sat under Regulatory
Services. With licensing, the
funding structure was aimed to be self-sustaining. There were set-up costs for renters’
rights, this would be monitored.
Once the Hosing Crisis had been declared, a Private Sector strategy
had been created for the City as there was a need to improve standards.
- Information could be provided on complaints received on housing
condition (including numbers of complaints), and on what has been
completed on HRA stock. Members
were encouraged to take details if people were dissatisfied with the way a
complaint was dealt with so the team could unpack it.
- Housing HHSRS checks were done as a random selection process
working clockwise around the City, picking 600 properties at a time. When they were completed, a further 600
were chosen. The properties chosen
included a mix of types of housing and were spread around the city.
- The team were praised for having provided a good response.
- With regard to queries on how on-track the service was to go from
C3 to C2, and on whether the housing regulator was measuring improvements
and impact on feedback form tenant’s scrutiny, it was noted that there
were inspections every four years, but the engagement process would mean
that the Regulator of Social Housing Team would not conclude their work
with the Council until the RSH were reassessed and moved the Council to a
new grade. They would likely
reassess over the next year. It was
important to give reassurance and evidence to the regulator that standards
are being met. Each month the
regulator was met with and updated with evidence from areas such as the
Tenants’ Scrutiny Panel. The annual
report from the Panel was also important evidence for the regulators. It was hoped that there would be a
re-grading going forward, but this could not be certain as it was
dependent on how actions were proceeded with.
- Regulators were pleased with progress, particularly with regard to
engaging people and training them and moving forward with the Tenant
Engagement Team.
- With regard to repairs, this was an ongoing challenge, particularly
with new legislation and additional demand. It was important to ensure external and
political visibility. It was
further noted that there were challenges in resource and in getting
companies to do the necessary work. Reports regarding Awaab’s Law and
Health and Safety Reports would go to the regulators as evidence.
- A manager and three officers had been recruited for tenant
engagement
- In terms of learning from best practice, feedback from complaints
had been analysed, and an annual report was produced in relation to
complaints. It was aimed to update IT systems to allow thematic reporting
as currently topic areas were manually extracted to ascertain where
complaints were coming from. The
Complaints Manager had done a deep dive with the Complaints team on
repairs, and a learning exercise had been conducted on different topic
areas to take forward and look at ways to have fewer complaints. The example of rat complaints was given
to illustrate how the service had learned from issues; the team had seen
that the system had not been working, so a specialist team was created and
a process initiated to block holes and work with pest controllers, as a
result, rat complaints were now very rare.
Best practice reports and maladministration issues were monitored,
and a quarterly report was received with topics identified as best
practice by the Ombudsman which was looked at with the Senior Management
Team in terms of whether action was needed and what form it should take.
- Every year a tenant satisfaction survey was required and last year
had shown an improvement on the year before. This survey was used to see where
investment was needed. The HRA
budget had proposals for capital investment to deal with complaints that
had been identified.
- In terms of the response rate on the survey, it was necessary to be
statistically compliant and undertake a specific number. A company had been procured to undertake
the Tenant Satisfaction survey and engage face-to-face, and the tenant
populace could be engaged with and barriers removed with regard to the
survey.
- With regard to increases in the repairs team, there was already a
large in-house team and we have worked to increase this. Work had been done to simplify the
recruitment process. A number of
agency staff had been brought on and then made permanent if they reach the
required standards. There were also
now up to 50 posts for craft apprenticeships.
- There were challenges around having an aging workforce and the
numbers replacing the team were just enough to keep afloat, but not enough
to deal with increasing demands, this was the reason contractors had
needed to be worked with. To ensure
compliance, it was necessary to have a more split approach. There was a preference for in-house, but
costs could be an issue. This was
an issue sector-wide and not just for local authorities.
- In response to a question about solar panels, it was explained that
there was currently no funding for them this year. Pressures on the HRA were significant as
there was a requirement to meet consumer standards and there was a need to
focus on this. It was hoped to do
more regarding climate change issues and retrofit stock in future
years. Lots of the stock was Energy
Performance Certificate C and there were dedicated officers to look at
retrofitting pathways.
AGREED:
1)
That members note the update.
2)
That additional information requested be
circulated.
3)
That comments made by members of this commission to
be taken into account.