The Director of Housing submitted a report to the Commission outlining
the requirements of Awaab’s Law and set out the division’s arrangements to
comply with the regulations underpinning Awaab’s law.
The Head of Service for Housing presented the item and the following was
noted:
- Phase
1 of Awaab’s Law came into force on 27th October 2025 with accompanying
non-statutory guidance.
- The
legislation represented a significant change for social landlords,
particularly in relation to damp and mould hazards, with a focus on tenant
safety and managing health and safety risks. Statutory response times of
24 hours, 5 working days and 10 working days were highlighted
- From
October 2026 Phase 2 of the regulations would be extended to cover hazards
which presented a significant risk of harm, including excess cold and
heat, falls, fire and electrical hazards, domestic and personal hygiene
and food safety.
- In
2027, Phase 3 of the regulations would cover all Housing Health and Safety
Rating System (HHSRS) hazards, apart from overcrowding where they
presented a significant risk of harm.
- Social
Landlords were required to investigate potential emergency hazards and, if
confirmed, undertake relevant safety work within 24 hours to make the
property safe.
- Potential
significant hazards were required to be investigated within 10 working
days.
- Tenants
would receive a written summary of findings within 3 working days of an
investigation concluding.
- If
a significant hazard was identified, safety work would begin within 5
days, and further follow on works must have started within 12 weeks of the
hazard being made safe.
- Implementation
had taken place during a period of high demand, particularly due to
increased reporting and seasonal cold weather.
- The
Council’s approach focused on identifying root causes of issues through a
range of repair responses, ensuring properties were made safe and enabling
resources to be targeted effectively to meet legislative requirements. It
was noted that processes, governance and oversight arrangements had been
adapted to support delivery.
- Performance
data indicated that 90% of emergency damp and mould cases had been
responded to within the 24 hour timeframe. A revised approach aimed to
ensure cases were assessed and reported within 3 days.
- Members
were advised that a dedicated damp and mould team had been established,
supported by additional budget growth of £170k to recruit cleaning staff
to address immediate risks.
- The
revised process, implemented from October 2025, required tenants to report
issues online or via telephone where necessary. All reports were assessed
to identify root causes and consider tenant vulnerabilities, supported by
a vulnerability matrix. Cases were categorised as emergency or significant
hazards, with required response times applied accordingly. It was
confirmed that properties were made safe within 24 hours where required,
and that temporary accommodation could be offered, although this had not
been required to date.
- Demand
had increased significantly beyond initial expectations. The phased
approach had supported prioritisation of emergency hazards and enabled
capacity to be built. Additional funding had been directed towards
contractors and resources to support compliance, with a hybrid delivery
model in place combining internal teams and external contractors.
- Improvements
to communication processes were outlined, including work to support
tenants in preventing damp and mould and to improve access and engagement.
Joint working across housing, social care and other services was taking
place to ensure risks were understood and managed effectively.
- Ongoing
work included reviewing processes to ensure compliance, regular reporting
to the senior management team, and engagement with the Tenant Scrutiny
Panel. Training and e-learning programmes had also been introduced to
improve staff understanding of damp and mould risks.
- Progress
since October 2025 had supported delivery of initial requirements and
positioned the Council to meet future phases, with a continued commitment
to improvement in response to demand and resource pressures.
In discussions with Members, the following was noted:
- Demand
had increased and this may reflect previous under reporting of damp and
mould issues. Information was available via the Council website outlining
how tenants could report issues, supported by ongoing engagement,
involvement of the Tenant Scrutiny Panel, and the development of
literature to improve awareness and prevention.
- It
was noted that a proportion of reported cases related to condensation
rather than structural damp, although these still required investigation
and resource to address within the required timescales, with additional
work undertaken to address non-structural contributing factors.
- The
challenges associated with damp and mould were highlighted, including the
impact of overcrowding and limited ventilation within properties. While
tenant behaviour could not be relied upon from a regulatory perspective,
there remained a need to support and educate residents on preventative
measures, particularly in the context of cost-of-living pressures.
- Concerns
were raised regarding the potential long-term impact of external wall
insulation and the importance of adequate ventilation. It was noted that
the most severe cases represented a small proportion of overall reports,
with approximately 1% identified as high level cases, and that no cases
had required alternative accommodation to date.
- It
was confirmed that medical needs, including those linked to damp and
mould, were taken into account within housing priority banding, and that
in severe cases tenants could be decanted and supported to move where
necessary. It was also noted that overcrowding remained a significant
factor in housing demand, and that assessments considered what was
reasonable within the context of household circumstances.
- It
was queried whether the requirements of Awaab's Law would extend to
private with implementation for the private sector anticipated around
2027.
- Concerns
were raised regarding specific property types and areas with known
ventilation issues, including whether there was a proactive approach to
identifying and addressing these, and whether sufficient interventions
such as dehumidifiers were being provided where required. It was reported
that approximately 3400 property inspections had been completed, enabling
identification of property types more prone to damp and mould and
supporting targeted planned maintenance programmes.
- It
was noted that specialist treatments, including spray systems such as TIC
Mould Control designed to eliminate mould spores, were being used and had
shown positive results in preventing recurrence.
- It
was highlighted that damp and mould cases could take time to resolve,
often requiring multiple visits to accurately diagnose and treat the
issue, and that cases remained open until fully resolved.
AGREED:
1)
That the Commission note the report.
2)
Information would be shared with Members to
support wider communication on damp and mould issues.